This is post 2 about the inspection of solar PV systems. If you have not read part 1, you can click here. This section of Senergia’s technical blog will address the following questions:
When an inspection is carried out for a private individual, the Consumer Services Act states: Section 55 An inspector referred to in Section 54 must have the experience and knowledge required for the assignment. He or she must carry out the assignment impartially and independently. This wording is relatively vague, so as the client you are advised to consider the knowledge an inspector should possess (see the later section of this technical blog post).
For an AB/ABT, it states: “An inspector may be a suitably qualified person appointed by the client, with the knowledge required for the assignment.” The procurement documents specify which company will carry out the inspection, and may also set additional requirements for the inspector, for example regarding experience, certification, etc.
Under KTjL, AB04 and ABT06. In short, what applies legally. For example, certification as a construction contract inspector through Kiwa or SBR is a significant advantage.
The inspector must have very good knowledge of how the solar PV system functions, both mechanically (the waterproofing layer, etc.) and electrically (PV string wiring, cable sizing, etc.).
Knowledge of how a system is inspected and which relevant aspects should be reviewed. Above all, however, knowledge of how to examine the system and which checks should be carried out.
Installation of solar PV systems is authorised work. The inspector must have knowledge of how an electrical installation works and is sized. In addition, they must have the appropriate authorisation within their electrical inspection and testing programme to inspect the entire solar PV system, both DC and AC.
In the construction and contracting sectors, two organisations issue certifications in construction contract law: Kiwa and SBR. Competence is verified through a certification process. It is important to note that the certification covers construction contract law only, not the technical aspects of the installation.
For an inspection of a construction contract under AB or ABT, it is relatively easy to find inspectors with the right expertise, as electrical inspections have long been carried out in, for example, both new-build projects and industry. However, you need to make sure that the inspector has the relevant expertise in solar PV installations.
For private individuals, it is considerably more difficult, as the supply of inspectors is limited. A good tip is to visit the industry association Svensk Solenergi, which has a database of inspectors. You can find them on their website: https://svensksolenergi.se/att-installera-solenergi/besiktning/. To be listed on Svensk Solenergi's website, inspectors must meet both the ethical requirements and the requirements regarding experience and knowledge. You can also search Kiwa and SBR for construction contract inspectors who have registered specialist expertise in solar PV installations.
There are many aspects of KtjL that are relevant to a solar PV project. This guide will not cover all of them. However, this chapter describes relevant provisions that apply to inspections for private individuals.
In principle, an inspection can be requested at any time within 10 years (under Section 17). The consumer may report defects up to 10 years after the assignment was completed, unless otherwise provided for by a guarantee or similar undertaking.
If the small-house project is not defective under Section 9, or the defects identified are of minor significance, the inspector must approve the project.
If the small-house project is not approved and the parties do not agree otherwise, a new final inspection must be carried out at a later date. The contractor must notify the inspector in good time when a new final inspection can be carried out.
If a final inspection is to be carried out under Section 53, the consumer has the right, notwithstanding the first paragraph of Section 41, to withhold 10 per cent of the agreed price until the small-house project has been approved under the second paragraph of Section 56.
No. A common solution is for the installer to rectify the defects and document the solution digitally (using photos or video). This is often a cost-effective solution for all parties.
It is uncommon for the contractor not to take responsibility. If the company is a member of Svensk Solenergi, you can contact them to put pressure on the company. However, there is no real means of applying pressure other than resolving the matter under civil law (i.e. in court). Consumers are protected by Swedish consumer laws.
The inspector’s most important task is to ensure that the client has received what was agreed and ordered. This means that the inspector must be given access to the design documentation and contract documents prepared for the construction project. This includes the purchase contract, snow and wind load calculations, simulation (e.g. in PV Sol or Helioscope), string layout drawing and inverter sizing documentation.
Below is a simplified list of the checks carried out by an inspector during an inspection.
We know it is not always easy to know which product or solution is best suited to you. Whether you have questions about our range, need guidance or would like help finding a solution tailored to your needs, we are here for you. With our knowledge and experience, we can help you make the right choice.