Introduction

This is post 2 about the inspection of solar PV systems. If you have not read part 1, you can click here. This section of Senergia’s technical blog will address the following questions:

  • Who is qualified to carry out an inspection?
  • How do I find an inspector?
  • How is an inspection carried out?

Who is qualified to carry out an inspection?

When an inspection is carried out for a private individual, the Consumer Services Act states: Section 55  An inspector referred to in Section 54 must have the experience and knowledge required for the assignment. He or she must carry out the assignment impartially and independently. This wording is relatively vague, so as the client you are advised to consider the knowledge an inspector should possess (see the later section of this technical blog post).

For an AB/ABT, it states: “An inspector may be a suitably qualified person appointed by the client, with the knowledge required for the assignment.” The procurement documents specify which company will carry out the inspection, and may also set additional requirements for the inspector, for example regarding experience, certification, etc.

What knowledge is required of an inspector?

Construction contract law

Under KTjL, AB04 and ABT06. In short, what applies legally. For example, certification as a construction contract inspector through Kiwa or SBR is a significant advantage.

Specialist knowledge of solar PV systems

The inspector must have very good knowledge of how the solar PV system functions, both mechanically (the waterproofing layer, etc.) and electrically (PV string wiring, cable sizing, etc.).

Inspection methodology

Knowledge of how a system is inspected and which relevant aspects should be reviewed. Above all, however, knowledge of how to examine the system and which checks should be carried out.

Electrical knowledge

Installation of solar PV systems is authorised work. The inspector must have knowledge of how an electrical installation works and is sized. In addition, they must have the appropriate authorisation within their electrical inspection and testing programme to inspect the entire solar PV system, both DC and AC.

Certified construction contract inspector

In the construction and contracting sectors, two organisations issue certifications in construction contract law: Kiwa and SBR. Competence is verified through a certification process. It is important to note that the certification covers construction contract law only, not the technical aspects of the installation.

How do I find an inspector?

For an inspection of a construction contract under AB or ABT, it is relatively easy to find inspectors with the right expertise, as electrical inspections have long been carried out in, for example, both new-build projects and industry. However, you need to make sure that the inspector has the relevant expertise in solar PV installations.

For private individuals, it is considerably more difficult, as the supply of inspectors is limited. A good tip is to visit the industry association Svensk Solenergi, which has a database of inspectors. You can find them on their website: https://svensksolenergi.se/att-installera-solenergi/besiktning/. To be listed on Svensk Solenergi's website, inspectors must meet both the ethical requirements and the requirements regarding experience and knowledge. You can also search Kiwa and SBR for construction contract inspectors who have registered specialist expertise in solar PV installations.

Important provisions for private individuals (KtjL)

There are many aspects of KtjL that are relevant to a solar PV project. This guide will not cover all of them. However, this chapter describes relevant provisions that apply to inspections for private individuals.

When can an inspection be requested?

In principle, an inspection can be requested at any time within 10 years (under Section 17). The consumer may report defects up to 10 years after the assignment was completed, unless otherwise provided for by a guarantee or similar undertaking.

Approved project?

If the small-house project is not defective under Section 9, or the defects identified are of minor significance, the inspector must approve the project.

Project not approved?

If the small-house project is not approved and the parties do not agree otherwise, a new final inspection must be carried out at a later date. The contractor must notify the inspector in good time when a new final inspection can be carried out.

How much can the client withhold?

If a final inspection is to be carried out under Section 53, the consumer has the right, notwithstanding the first paragraph of Section 41, to withhold 10 per cent of the agreed price until the small-house project has been approved under the second paragraph of Section 56.

Is a reinspection (new final inspection) necessary?

No. A common solution is for the installer to rectify the defects and document the solution digitally (using photos or video). This is often a cost-effective solution for all parties.

What should you do if you cannot reach an agreement with your installer after an inspection?

It is uncommon for the contractor not to take responsibility. If the company is a member of Svensk Solenergi, you can contact them to put pressure on the company. However, there is no real means of applying pressure other than resolving the matter under civil law (i.e. in court). Consumers are protected by Swedish consumer laws.

Inspection methodology

The inspector’s most important task is to ensure that the client has received what was agreed and ordered. This means that the inspector must be given access to the design documentation and contract documents prepared for the construction project. This includes the purchase contract, snow and wind load calculations, simulation (e.g. in PV Sol or Helioscope), string layout drawing and inverter sizing documentation.

What should be checked during an inspection?

Below is a simplified list of the checks carried out by an inspector during an inspection.

  1. That a contract/agreement is in place, and any tender documents.
  2. That there is an operation and maintenance folder explaining, among other things, how the installation should be maintained and which components are included.
  3. Self-inspections of the work carried out.
  4. Snow and wind load calculations, or other structural calculations.
  5. How it has been installed, for example on a roof, in a solar farm, on a façade or similar.
  6. Warranty terms.
  7. Insulation and short-circuit current measurements in accordance with HB 444 Chapter 6 and HB 457 Section 26.2.
  8. Check the AC/DC cabling to ensure that nothing is in contact with sharp edges, etc., and that it is properly secured.
  9. Positioning and installation of the snow guards. See BBR 29 Chapter 8.2434.
  10. Any earth electrode and its accompanying documentation, applicable to installations operating in island mode.

Need help finding the right option?

We know it is not always easy to know which product or solution is best suited to you. Whether you have questions about our range, need guidance or would like help finding a solution tailored to your needs, we are here for you. With our knowledge and experience, we can help you make the right choice.

Related posts

Technology blog

New rules for functional earthing

In a short time, functional earthing has gone from being a niche issue for particularly interested installers to becoming a central part of how solar installations should be designed, installed and inspected. With new shared guidelines and clarified pra...
Technology blog

Inspection 1 – Construction contract law

There is lively debate in the Swedish solar industry about what constitutes a correctly installed solar PV system. The answer depends on the circumstances. In other words, the applicable legislation and the type of contract entered into both affect how...
Technology blog

Five mistakes (fatal mistakes) when installing solar panels

There is an ongoing debate in Sweden’s solar industry, where organisations such as RISE, the Swedish Electrical Safety Authority, Länsförsäkringar and even SVT have published articles about incorrect and downright dangerous solar installations. Senergia...

This website uses cookies

Cookies ("cookies") consist of small text files. The text files contain data which is stored on your device. To be able to place some type of cookies we need your consent. We at Senergia AB, corporate identity number 556969-6023 use these types of cookies. To read more about which cookies we use and storage duration, click here to get to our cookiepolicy.

Manage your cookie-settings

Necessary cookies

Check to consent to the use of Necessary cookies
Necessary cookies are cookies that need to be placed for fundamental functions on the website to work. Fundamental functions are for instance cookies that are needed for you to use menus and navigate the website.

Statistical cookies

Check to consent to the use of Statistical cookies
To know how you interact with the website we place cookies to collect statistics. These cookies anonymize personal data.

Ad measurement cookies

Check to consent to the use of Ad measurement cookies
To be able to provide a better service and experience we place cookies to tailor marketing for you. Another purpose for this placement is to market products or services to you, give tailored offers or market and give recommendations on new concepts based on what you have bought from us previously.

Ad measurement user cookies

Check to consent to the use of Ad measurement user cookies
In order to show relevant ads we place cookies to tailor ads for you

Personalized ads cookies

Check to consent to the use of Personalized ads cookies
To show relevant and personal ads we place cookies to provide unique offers that are tailored to your user data